Dalgaranga on time and budget – Gascoyne

November 5, 2017

Responsive image

The Dalgaranga gold project, in Western Australia, is on scheduled for first gold production in the second quarter of 2018, with the project currently on budget, ASX-listed Gascoyne Resources said on Friday.

The design and engineering of the 2.5-million-tonne-a-year processing plant was about 91% complete, while construction of the tailings storage facility was 75% complete.