PLS Group has approved a roughly A$1.9 billion lithium expansion at Pilgangoora in Western Australia, committing to its largest investment decision as a revised mine plan brings previously uneconomic material into the reserve base.
The P2000 project aims to raise annual spodumene production capacity to approximately 2 million tonnes, with first production targeted for the September quarter of 2029. The decision announced on October 16 pairs that processing expansion with a larger mining inventory, including Pilgangoora’s first underground Ore Reserve.
PLS reported total Ore Reserves of 249.2 million tonnes grading 1.24% lithium oxide, or Li₂O, containing about 3.1 million tonnes of Li₂O. According to the company’s October presentation, reserve tonnage rose 23%, while contained lithium increased 31%. The faster increase in contained metal indicates that the revised inventory adds grade as well as tonnes.
P2000 changes which Pilgangoora tonnes can be mined economically
The most consequential reserve detail is the approximately 67 million tonnes previously classified as waste that can now be recovered economically as ore under the P2000 plan. That makes this week’s announcement more than a processing-capacity decision: the expansion changes the economic boundaries of the deposit.
An Ore Reserve is the economically mineable portion of a deposit under a defined set of technical and commercial assumptions. It can therefore grow through a revised development plan, rather than through drilling alone. At Pilgangoora, the new plan allows material excluded from earlier ore schedules to contribute to future production.
The 67 million tonnes shouldn’t be read as a matching net increase in the total reserve. Reserve comparisons also reflect depletion and other changes between estimates. Nor does the reclassification mean all those tonnes have the same grade, recovery or mining cost as the existing inventory.
Historical comparisons require similar care. PLS’s earlier major reserve update reported 214 million tonnes after a 55-million-tonne increase announced in August 2023. The company’s 2025 annual report subsequently adjusted that inventory for depletion. Consequently, the newly reported 23% increase should not be calculated directly against the older 214-million-tonne headline figure.
For the industry, the distinction matters. P2000 illustrates how expanding an established operation can unlock additional feed within its existing deposit. That offers a different route to supply growth from developing a separate mine, although construction, operating costs and lithium-market conditions will still determine the expansion’s economic outcome.
Higher-grade underground reserve adds a second mining horizon
Pilgangoora’s updated inventory includes a maiden underground Ore Reserve of 46.5 million tonnes at 1.50% Li₂O, according to PLS’s October 16 presentation. That grade is about 21% higher than the combined reserve grade of 1.24%, based on the reported figures.
The underground component represents approximately 19% of total reserve tonnage. Its higher grade means it accounts for a larger share of contained lithium, about 23% by calculation. Those proportions make underground mining a material part of the long-term inventory, rather than a marginal extension.
Grade alone doesn’t establish whether underground tonnes will deliver better margins. Underground development has different access, scheduling and operating requirements from open-pit mining. The reserve establishes an economically assessed inventory under the company’s assumptions; it does not make the two mining methods interchangeable.
PLS says the expanded open-pit reserve supports roughly 20 years of production under the P2000 plan. Incorporating underground mining could take that beyond 25 years. The distinction is important: the longer horizon depends on bringing the underground component into the operating sequence, rather than simply extending the existing open-pit schedule.
2029 production target leaves construction and ramp-up ahead
Pilgangoora is wholly owned by PLS and lies in Western Australia’s Pilbara region. That ownership gives the company full exposure to the expansion’s capital requirements and operating results.
The approximately A$1.9 billion capital program includes previously approved expenditure incurred before the final investment decision, but excludes separately approved infrastructure spending. It therefore should not be treated as an all-inclusive figure for every associated development commitment, or as expenditure that remains entirely ahead of the company.
The September-quarter 2029 first-production target also needs to be distinguished from achieving approximately 2 million tonnes of annual capacity. Starting production and reaching sustained nameplate output are separate milestones. Likewise, spodumene concentrate tonnage is not equivalent to contained lithium oxide or finished lithium chemicals.
For the coming months, the central question shifts from project approval to execution: how PLS advances construction, integrates the revised ore schedule and preserves the timetable for first production. The enlarged reserve provides a longer feed horizon, but the industry supply implications will depend on when the new capacity reaches sustained output, not simply when it is commissioned.