Platinum miner Wesizwe Platinum remains within its targeted concentrate production output and project construction costs budget for its flagship Bakubung project, in Rustenburg. Reporting on its 2015 financial year performance, the Chinese-backed company said that, during the year to December, the main and ventilation shafts were completed as scheduled at 825 m and 810 m respectively. Further, services projects on site were on schedule, with an additional 20 MWa secured for the phase one power supply for the commissioning of the shafts and 1.5-million-litres-a-day capacity had been commissioned for permanent water supply to the mine.